33 billion MNT for road construction in Zamiin-Uud

2013 оны 4 сарын 1

Prime Minister Norov Altankhuyag gave the order to intensify construction work to extend the bottleneck transportation load at Zamiin-Uud border crossing and to complete the customs control complex. It is designed to pass trucks through a 2.3 km customs control road due to be completed in June.

Issues surrounding the completion of the construction work were discussed  during a regular cabinet meeting on Sunday March 31st.

The Government signed a direct agreement to build the road in Zamiin-Uud by June 15th, financing the project through the Development Bank.

The Government also gave orders to build an 8.7 km road from the customs controlled X ray area to the transit terminal and truck road for October 15th this year.

 The Development Bank will be responsibility for financing 33 billion MNT of the project.